Design Of Triang Water Supply Scheme

Scope of works

  • Study of Triang Water Demand till the year 2020
  • Detailed Design of New 55 mld Water Treatment Plant including the intake works.

Detailed design of distribution mains and balancing reservoirs

Contract Value : RM33,000,000.00
Capacity : 55 MLD
Date of Site Possession : 1999
Date of Completion : 2004